PT KLJ required replacement industrial batteries for the PLN UPDK Keramasan facility with FIAMM SDH series specification for the 2026 substation maintenance cycle. Primary challenge: direct sourcing from Italy within a 12-week window with guaranteed authenticity and TKDN documentation.
Bearose executed dual-track sourcing direct contact with FIAMM Italy in parallel with regional distributor stock verification to ensure on-time delivery. Customs clearance was handled through a verified freight forwarder under DDP terms.
After delivery, Bearose's technical team supervised commissioning on site and ensured each unit was registered for the global FIAMM warranty. This project became the anchor for a long-term partnership with PLN South Sumatra Region for the next maintenance cycle.